1. CBMPPs are submitted by the engineer of record for the project, along with other applicable engineering plans to the Engineering Department, where they are reviewed by the Graduate Engineer, Stormwater Coordinator, City Inspector, and other Departments (Utilities, Fire, Building, etc.) as required by plan content.
  2. Once the plans have been approved, a pre-construction meeting with the developer, contractor, and engineer of record is scheduled by the Graduate Engineer.
  3. The City of Phenix City Engineering Department will issue the Land Disturbing Permit at Plan Approval, after all other required State and Federal Permits have been obtained and copies submitted to the Engineering Department. At this time, construction may begin. The City of Phenix City Engineering Department requires 72 hour notice before construction begins.
  4. Once all BMPs have been properly installed, the contractor calls the Stormwater Coordinator to arrange for a site inspection of all BMPs. BMP installation is required to be completed  before mass grading/construction begins.